Home, <- Previous page

"INNOVATIVE ECOLOGICAL MINERAL DRESSING TECHNOLOGIES"


Equipment. Workshops

PRELIMINARY DRESSING WORKSHOP (600 tons/hour)

Front viewLeft-side view

1,2,3 - line with unload trolleys for pieces delivery (size class -50+25 mm (1), -25+12 mm (2) and -12+0 mm (3);
4,5,6 - accumulating bins for loading (size class -50+25 mm (4), -25+12 mm (5) and -12+0 mm (6);
7 - container control units;
8,9 - separation container ("left" option (8) and "right" option (9));
10 - line for collection and output of ore;
11 - line for collection and output of bulk;
12 - crane.










PRELIMINARY DRESSING WORKSHOP SECTION.

1
- unsorted ore supply line;
2 - load bin;
3,4 - containers with separation units ("left" option (4) and "right" option (3));
5 - shaking feeders;
6 - analyzer;
7 - valve unit;
8,9 - lines for collection of tailings (8) and concentrate (9).